Day 1-2

Pre-Install. Pool Layout.

In this phase we layout the pool in your back yard with our template layout system. We can move the pool location within the back yard to meet your specific pool placement. Many times the first location may not be the optimal spot. No problem. We just move the template. This gives you the perfect visual placement of the pool before we dig.

i1.jpg

i2.jpg

i3.jpg

Excavation

This can take up to 2 days depending on soil conditions, lot size, and dirt removal.
We realize not all lots are the same so we size the excavation equipment accordingly.

 

Day 3-4

Set Grade, Set Pool, and Fill

i4.jpg

i5.jpg

Once the pool is set to grade we start filling. Depending on the pool size and water pressure, this can take up to 2 days. Once the pool is filled, you can take the first dip.

 

Day 5-6

Grade for Deck, Set Equipment, Install Electrical Service and Test Plumbing

i6.jpg

All pools are installed to International building codes. All plumbing and electrical are tested. Pool chemistry is tested for alkalinity level, Ph balance, and chlorine.

 

Day 7-10

Pour Concrete Deck and Kool Deck Surface Finish

i8.jpg

The deck is in the final phase of construction. We pore the concrete and Spray Deck.

Spray Deck is cool to the touch even in hot sunlight. It is available in multiple colors and patterns.

 


Office: (972) 436-7300

E-mail Us

 

 

 

Web Site Design & Maintenance by:
Double S Designs